The foundations are being wrapped up, new concrete sidewalks are being poured, and the 13 modular building sections are in the midst of being delivered. The modular buildings are manufactured in California and transported from the
Central Valley on flatbed tractor trailer trucks. Due to the size and logistics, only two modular components are delivered each day causing traffic delays primarily on Butterfield Road.