Warning: count(): Parameter must be an array or an object that implements Countable in /home/rossva5/public_html/administrator/components/com_poweradmin/models/menuitem.php on line 376

Warning: count(): Parameter must be an array or an object that implements Countable in /home/rossva5/public_html/administrator/components/com_poweradmin/models/menuitem.php on line 376

Warning: count(): Parameter must be an array or an object that implements Countable in /home/rossva5/public_html/administrator/components/com_poweradmin/models/menuitem.php on line 376

Warning: count(): Parameter must be an array or an object that implements Countable in /home/rossva5/public_html/plugins/system/jsnpoweradmin/jsnpoweradmin.php on line 224

Warning: count(): Parameter must be an array or an object that implements Countable in /home/rossva5/public_html/administrator/components/com_poweradmin/models/menuitem.php on line 376

Warning: count(): Parameter must be an array or an object that implements Countable in /home/rossva5/public_html/plugins/system/jsnpoweradmin/jsnpoweradmin.php on line 257

Warning: count(): Parameter must be an array or an object that implements Countable in /home/rossva5/public_html/libraries/cms/application/cms.php on line 471
Construction Update: January 2013

Warning: count(): Parameter must be an array or an object that implements Countable in /home/rossva5/public_html/administrator/components/com_imageshow/classes/jsn_is_showcasetheme.php on line 294

Manor Elementary School Modular Building Completed

Construction of the Modular Classroom at Manor Elementary School to accommodate the increased enrollment began approximately on January 9, 2012 and was successfully completed on March 5, 2012.  The students were able to enjoy and make use of the new classroom at the start of the 2012/13 school year.

OTher Manor Elementary School Updates

The Board of Trustees (BOT) approved pre-design plans for Manor Elementary have been advanced to the Schematic Design Phase.  Preliminary cost estimates indicate that further review is necessary to determine the feasibility of implementing the Schematic Design.  Concurrently, the BOT requested the Facilities Master Plan (FMP) be updated to confirm the decisions regarding the development and design at each site.  The FMP was presented to the BOT at the January 08, 2013 school board meeting.

The approved plan places two new classrooms at the front of the school and modifies the parking/drop-off area.

Manor Approved Option E - 1/10/2012

Brookside Elementary School (formerly known as Brookside Lower)

The BOT approved pre-design plans for Brookside Elementary have been advanced to the Schematic Design Phase.  Preliminary cost estimates indicate that further review is necessary to determine the feasibility of implementing the Schematic Design.  Concurrently, the BOT requested the FMP be updated to confirm the decisions regarding the development and design at each site.  The FMP was presented to the BOT at the January 08, 2013 school board meeting.

The design includes five classrooms, a new Multipurpose Room and some hardscape modifications.

Brookside Lower Approved Pre-Design - 1/10/2012

Hidden Valley Elementary School (formerly known as Brookside Upper)

The BOT approved pre-design plans for Hidden Valley Elementary have been advanced to the Schematic Design Phase.  Preliminary cost estimates indicate that further review is necessary to determine the feasibility of implementing the Schematic Design.  Concurrently, the BOT requested the FMP be updated to confirm the decisions regarding the development and design at each site.  The FMP was presented to the BOT at the January 08, 2013 school board meeting.

The approved plan will convert the existing library pod into kindergarten complex (3 classrooms with restroom), create a kinder play area, build a new library at the front of the school and replace one of the existing portables with a modular classroom building, improvements for a pedestrian pathway, ramps and  parking lot modifications are in the scope of work.

Hidden Valley Approved Pre-Design - 1/10/2012

Hidden Valley Elementary School Kinder Play Yard Completed

Construction of the kindergarten play area at Hidden Valley Elementary School began on June 08, 2012 and was successfully completed approximately July 13, 2012.  The students were able to enjoy the new play area at the start of the 2012/13 school year.

Wade Thomas Elementary School

The BOT approved pre-design plans for Wade Thomas Elementary have been advanced to the Schematic Design Phase.  Preliminary cost estimates indicate that further review is necessary to determine the feasibility of implementing the Schematic Design.  Concurrently, the BOT requested the FMP be updated to confirm the decisions regarding the development and design at each site.  The FMP was presented to the BOT at the January 08, 2013 school board meeting.

The approved plan will add four classrooms along Ross Avenue and maximizes the playground space for student use.

Wade Thomas Approved Option C - 1/10/2012

White Hill Middle School Update

Division of State Architect (DSA) approval of the plans was received in July, 2012.  Plant Construction was given the notice to proceed on June 08, 2012 and started construction on June 11, 2012.  Since the start of construction, the renovations to the 100 & 300 Building are complete and being enjoyed by the students this school year.  13 temporary portable classrooms were installed to provide necessary teaching space during the construction of the new 7th and 8th grade Buildings.  Because the temporary classrooms were located on the existing basketball courts, new courts were installed near the sports fields.  Site and Hex-Plex classrooms demolition was completed very quickly.  The earthwork started immediately after the demolition work was complete, and concrete for the footings and foundations was placed in October.  This was a major milestone in the construction schedule.  Steel for the 7th & 8th grade buildings started arriving and being erected in early December, 2012.  The steel for both buildings is in place, marking another major milestone.  The steel is the structural support for the buildings, and provides a visible and tangible representation of the new buildings.

White Hill Plans 1/10/2012

      

 

COC Meeting

The COC met on October 17, 2012 and toured Manor Elementary School and White Hill Middle School to review and receive an update on the construction progress.  The COC reviewed the current Measure A Financial Report for the 2nd Sale of Bonds, Form 21, Unaudited Actuals, which are the basis for the 2011/2012 Performance and Financial Audits.  The next COC meeting is scheduled for February 13, 2013 at 5:00 PM at the Ross Valley District Office.  The COC is scheduled to submit a draft annual report at this meeting.

Common Core

commoncorelogoLearn about Common Core Standards and their integration into the Ross Valley classroom.

Read more...

Construction Updates

constructionlogoWe're updating all our facilities to meet 21st Century learning needs.

Read More...

District and School Calendars

districtcalendarlogoGoogle calendar of important school events, vacations and more.

Read More...

Go to top