The Ross Valley School District Board hired the following firms to provide architectural planning and design services for the new construction at White Hill Middle School.
WRNS Studio
WRNS Studio is providing architectural planning and design services for the new construction of White Hill Middle School.
QKA
QKA will provide architectural planning and design services for the new construction of Hidden Valley and Brookside.
White Hill Middle School is currently under construction and the District expects accept the new classroom buildings as completed in late-October 2013 and occupy them in November 2013. The District and Architects conducted meetings with staff, parents and community members to solicit input on all four elementary school sites. Based on this input, the architects have developed the preliminary elementary school plans below.
The pre-design plans for Brookside Elementary were moved to the Schematic Design Phase. The work for this project, which includes five classrooms, a new Multipurpose Room and some hardscape modifications, has been split into two phases. The first phase, which is currently in design development, includes the construction of 5 new classrooms. This project will use modular classroom buildings that are expected to be ready for student occupancy for the 2014-2015 school year. The new multi-purpose building is in the project's second phase. A timeline for the second phase will be set after the sale of the next series of bonds.
Brookside Lower Approved Pre-Design - 1/10/2012
The plans for Hidden Valley Elementary were advanced to the Schematic Design Phase and preliminary cost estimates have indicated that further review is necessary to determine the feasibility of implementing the Schematic Design. The District has temporarily reduced the design effort for this campus and a revised plan will be discussed following the sale of the next series of bonds.
Construction of the kindergarten play area at Hidden Valley Elementary School began on June 08, 2012 and was successfully completed approximately July 13, 2012. The students were able to enjoy the new play area at the start of the 2012-2013 school year.
Hidden Valley Approved Pre-Design - 1/10/2012
The Board of Trustees (BOT) approved pre-design plans for Manor Elementary have advanced to the Schematic Design Phase and preliminary cost estimates indicate that further review is necessary to determine the feasibility of implementing the Schematic Design. The design for this campus has changed and further work awaits the results of the Board of Trustees decision regarding the possible relocation of the Multi-Age Program currently located at Manor.
Manor Approved Option E - 1/10/2012
The pre-design plans for Wade Thomas Elementary were advanced to the Schematic Design Phase and preliminary cost estimates indicate that further review is necessary to determine the feasibility of implementing the Schematic Design. Further design work on this campus is currently in a holding pattern pending the sale of the next series of bonds and the outcome of the decision regarding the location of the Multi-Age Program.
Wade Thomas Approved Option C - 1/10/201
White Hill Middle School